There’s been a lot of talk (no thanks to Cisco/EMC) about infrastructure blocks recently. Myself I never (and still don’t) like the concept. I think it makes sense in the SMB world where you have very limited IT staff and they need a canned, integrated solution. Companies like HP and IBM have been selling these sorts of mini stacks for years. As for Microsoft I think they have a “Small business” version of their server platform which includes a bunch of things integrated together as well.

I think the concept falls apart at scale though, I’m a strong believer in best of breed technologies, and what is best of breed really depends on the requirements of the organization. I have my own favorites of course for the industries I’ve been working with/in for the past several years but I know they don’t apply to everyone.

I was reading up yesterday on some new containerized data centers that SGI released in their Ice Cube series. The numbers are just staggering.

In their most dense configuration, in 320 square feet of space consuming approximately 1 megawatt of power you can have either:

  • More then 45,000 CPU cores
  • More than 29 Petabytes of storage

In both cases you can get roughly 45kW per rack, while today most legacy data centers top out at between 2-5kW per rack.

Stop and think about that for a minute, think about the space, think about the density. 320 square feet is smaller than even a studio apartment,, though in Japan it may be big enough to house a family of 10-12 (I hear space is tight over there).

How’s that for an infrastructure block? And yes you can stack one on top of another

ICE Cube utilizes an ISO standard commercially available 9.5′ x 8′ x 40′ container. SGI intentionally designed the offering such that the roof of the container is clear of obstruction and fully capable of utilizing its stacking container feature. Because of this, SGI is positioned to supply a compelling density multiplier for future expansion of the data center. If installed in a location without overhead height restriction the 9.5′ x 8′ x 40′ containers in our primary product offering can be stacked up to three-high, thus allowing customers to double or triple the per square foot density of the facility over the already industry-leading density of a single ICE Cube.

All of this made me think of a particular scene from a ’80s movie.

Really makes these other blocks some vendors are talking about sound like toys by comparison doesn’t it.

May 3, 2010

Terremark vCloud Express: First month

Filed under: Datacenter,Virtualization — Tags: , , — Nate @ 3:02 pm

Not much to report, got my first bill for my first “real” month of usage (minus DNS I haven’t gotten round to transferring DNS yet but I do have the ports opened).

$122.20 for the month which included:

  • 1 VM with 1VPU/1.5GB/40GB – $74.88
  • 1 External IP address – $0.00 (which is confusing I thought they charged per IP)
  • TCP/UDP ports – $47.15
  • 1GB of data transferred – $0.17

Kind of funny the one thing that is charged as I use it (the rest being charged as I provision it) I pay less than a quarter for. Obviously I slightly overestimated my bandwidth usage. And I’m sure they round to the nearest GB, as I don’t believe I even transferred 1GB during the month of April.

I suppose the one positive thing from a bandwidth and cost standpoint if I ever wanted to route all of my internet traffic from my cable modem at home through my VM (over VPN) for paranoia or security purposes, I could. I believe Comcast caps bandwidth at ~250GB/mo or something which would be about $42/mo assuming I tapped it out(but believe me my home bandwidth usage is trivial as well).

Hopefully this coming weekend I can get around to assigning a second external IP, mapping it to my same DNS and moving some of my domains over to this cloud instead of keeping them hosted on my co-located server. Just been really busy recently.

May 1, 2010

Data Center trailer parks

Filed under: Datacenter — Nate @ 10:30 am

OK, probably going further out on a limb here but for some reason the idea came to my head and I thought it would be a funny concept.

With all these new things coming up around container based data centers, there still remains a problem that needs to be solved – where do you get the power, cooling and networking.

So I imagined a trailer park of sorts for data centers where companies could drive their container data centers(which can contain well over one thousand systems per container) and plug them in to a network jack and get power, and a water feed.

Data centers of the future may end up just being giant parking lots (above or below ground) with some sort of industrial grade easy to use connectors for plug and play containers. Maybe it goes even further and you are billed on just what you use automatically. A Ethernet jack or perhaps wireless connection at the site and you could authenticate to the facility and provision bandwidth, IP addresses, and plug in and turn on. The system would automatically meter the amount of water you draw, and perhaps even monitor the temperature of the return water feed (those that return it cooler will get charged less). And of course pay per kWH for power. Plus a flat rate fee for parking.

Maybe power companies, water treatment facilities(or other common water provider) and carriers team up to provide some sort of common standard or technique to provide this kind of service.

Then perhaps add in IPv6, I think I’ve read about it having some good IP mobility features, or maybe you just get some sort of BGP feed where you can advertise your own IPs.

Then say some disaster strikes like a hurricane or earthquake, the facility is robust enough to handle it, but maybe the infrastructure around it is destroyed, go pick up your container and take it to another lot.

By the time I got mid way through this post the concept in my mind sounded more feasable than it was when it first came to mind.

April 30, 2010

Violate Electrical specs for more servers?

Filed under: Datacenter,General,Random Thought — Tags: — Nate @ 8:46 pm

As usual on big blog posts I often literally go back and re-read the post about 60 times and think about what I wrote.

Well I was reading my most recent post about Datacenter Dynamics specifically the stranded power section and the datacenter operators of hyperscale facilities wanting to draw every watt they can off the circuits to maximize efficiency and I got to thinking..

Would they go so far as to violate electrical specs by drawing more than 80% of the power for a particular circuit? I mean in theory at least if they construct the components properly they can probably do it fairly safely. I learned a few years ago from someone, that the spec in question is NEC Section 384-16(c). Which I think in part reads:

The NEC requires the branch circuit computed load for conductor sizing to be sized at 125% of the continuous load, plus the noncontinuous load (100%).

Which equates to 80% utilization. If you know your power usage levels that well, and your loads etc, do you think such hyperscale facilities would run at 85%? 90%? 95% of circuit load? Really with all of the other extreme measures being taken to maximize efficiency I wouldn’t put it past them. They’re going so far as to design special motherboards and have specific components down to the VRMs to lower power usage. I can see them investing in higher grade electrical gear allowing them to safely operate at higher circuit draws, especially when you take into account power capping as well. Afterall, if your spending the effort to shave literally single digit watt usage off your systems that extra 20% capacity on the circuit has to be very tempting to use.

I remember a few years ago doing a load test on one of the aforementioned lower quality power strips(they weren’t cheap, but the company’s QA wasn’t up to par), it was a 30A PDU. And I loaded it up with a bunch of systems, and walked away for a couple minutes and came back and was shocked to see the meter reporting 32A was being drawn. I immediately yanked some of the power cords out to get it back under 30A. After talking with the manufacturer (or maybe it was another manufacturer I don’t recall), they said that was not unexpected, the breaker has some sort of internal timer that will trip based on the amount of excess load on the circuit, so if your drawing 30A it probably won’t trip for a while, if your drawing 32A then it may trip after a few minutes, if you try to draw 40A it will likely trip immediately(I’m guessing here).

April 29, 2010

Datacenter Dynamics

Filed under: Datacenter,Events — Nate @ 7:09 pm

For the past couple of years the folks behind the Datacenter Dynamics conferences have been hounding me to fork over the $500 fee to attend their conference. I’ve looked at it, and it really didn’t seem aimed at people like me, aimed more for people who build/design/manage data centers. I mostly use co-location space. While data center design is somewhat interesting to me, at least the leading edge technology it’s not something I work with.

So a couple days ago a friend of mine offered to get me in for free so I took him up on his offer. Get away from the office, and the conference is about one mile from my apartment.

The keynote was somewhat interesting, given by a Distinguished Engineer from Microsoft. I suppose more than anything I thought some things he had to say were interesting to note. I’ll skip the obvious stuff, he had a couple of less obvious things to say –

Let OEMs innovate

One thing he says MS does is they have a dedicated team of people that instrument subsets of their applications and servers and gather performance data(if you know me you probably know I collect a lot of stats myself everything from apps, to OS, to network, load balancers, power strips, storage etc).

They take this data and build usage profiles for their applications and come up with as generic as possible yet still being specific on certain areas for their server designs:

  • X amount of CPU capacity
  • X amount of memory
  • X amount of disk
  • X amount of I/O
  • Power envelope at a per-rack and per-container basis
  • Operational temperature and humidity levels the systems will operate in

He raised the point if you get too specific you tie the hands of the OEMs and they can’t get creative. He mentioned that on a few occasions they sent out RFPs and gotten back very different designs from different OEMs. He says they use 3 different manufacturers (two I know are SGI/Rackable and Dell, don’t know the third). They apparently aren’t big enough to deal with more OEMs (a strange statement I thought) so they only work with a few.

Now I think for most organizations this really isn’t possible, as getting this sort of precise information isn’t easy, especially from the application level.

They seem to aim for operating the servers in up to mid 90 degree temperatures. Which is pretty extreme but these days not too uncommon among the hyper scale companies. I saw a resume of a MS operations guy recently that claimed he used monitoring software to watch over 800,000 servers.

They emphasized purpose built servers, eliminating components that are not needed to reduce costs and power usage, use low power processors regardless of application. Emphasis on performance/watt/TCO$ I think is what he said.

Stranded Power

Also emphasized eliminating stranded power, use every watt that is available to you, stranded power is very expensive. To achieve this they leverage power capping in the servers to get more servers per rack because they know what their usage profile is they cap their servers at a certain level. I know HP has this technology I assume others do too though I haven’t looked. One thing that was confusing to me when quizzing the HP folks on it was that it was server or chassis(in the case of blades) level. To me that doesn’t seem very efficient, I would expect it to at least be rack/circuit level. I mean if the intelligence is already in the servers you should be able to aggregate that intelligence outside the individual servers to operate more as a collective, to gain even more efficiencies. You could potentially extend the concept to the container level as well.

Idle servers still draw significant power

In my own experience measuring power levels at the PDU/CDU level over the past 6 years I have seen that typical power usage fluctuates at most 10-15% from idle to peak(application peak not really server peak). This guy from MS says that even with the most advanced “idle” states the latest generation CPUs offer it only reduces overall power usage to about 50% of peak. So there still seems to be significant room for improving power efficiencies when a system is idle. Perhaps that is why Google is funding some project to this end.

MS’s Generation 4 data centers

I’m sure others have read about them, but you know me, I really don’t pay much attention to what MS does, really have not in a decade or more so this was news to me..

He covered their evolution of data center design, topping out at what he called Gen3 data centers in Chicago and Ireland, container based.

Their generation 4 data centers are also container based but appear to be significantly more advanced from an infrastructure perspective than current data center containers. If you have silverlight you can watch a video on it here, it’s the same video shown at the conference.

I won’t go into big details I’m sure you can find them online but the basics is it is designed to be able to operate in seemingly almost any environment, using just basic outside air for cooling. If it gets too hot then a water system kicks in to cool the incoming air(an example was lowering ~105 degree air outside to ~95 degree air inside cool enough for the servers). If it gets too cold then an air re-circulation system kicks in and circulates a portion of the exhaust from the servers back to the front of the servers to mix with incoming cold air. If it gets too humid it does something else to compensate(forgot what).

They haven’t deployed it at any scale yet so don’t have hard data on things yet but have enough research to move forward with the project.

I’ll tell you what I’m glad I don’t deal with server hardware anymore, these new data centers are running so hot I’d want them to run the cooling just for me, I can’t work in those temperatures I’d die.

Server level UPS

You may of heard people like Google talking about using batteries in their servers. I never understood this concept myself, I can probably understand not using big centralized UPSs in your data center, but I would expect the logical move would be to rack level UPSs. Ones that would take AC input and output DC power to the servers directly.

One of the main complaints about normal UPSs as far as efficiency goes is the double conversion that goes on, incoming AC converts to DC to the batteries, then back to AC to go to the racks. I think this is mainly because DC power isn’t very good for long distances. But there are already some designs on the market from companies like SGI (aka Rackable) for rack level power distribution(e.g. no power supplies in the servers). This is the Cloudrack product, something I’ve come to really like a lot since I first got wind of it in 2008.

If you have such a system, and I imagine Google does something similar, I don’t understand why they’d put batteries in the server instead of integrate them into the rack power distribution, but whatever it’s their choice.

I attended a breakout session which talked about this topic presented by someone from the Electric Power Research Institute. The speaker got pretty technical into the electrical terminology beyond what I could understand but I got some of the basic concepts.

The most interesting claim he made was that 90% of electrical disruptions last less than two seconds. This here was enough for me to understand why people are looking to server-level batteries instead of big centralized systems.

They did pretty extensive testing with system components and power disruptions and had some interesting results, honestly can’t really recite them they were pretty technical, involved measuring power disruptions in the number of cycles(each cycle is 1/60th of a second), comparing the duration of the disruption with the magnitude of it(in their case voltage sags). So they measured the “breaking” point of equipment, what sort of disruptions can they sustain, he said for the most part power supplies are rated to handle 4 cycles of disruption, or 4/60ths of a second likely without noticeable impact. Beyond that in most cases equipment won’t get damaged but it will shut off/reboot.

He also brought up that in their surveys it was very rare that power sags went below 60% of total voltage. Which made me think about some older lower quality UPSs I used to have in combination with auto switching power supplies. What would happen when the UPS went to battery it caused a voltage spike, which convinced the auto switching power supplies to switch from 120V to 208V and that immediately tripped their breaker/saftey mechanism because the voltage returned to 120V within who knows how many cycles. I remember when I was ordering special high grade power supplies I had to request that they be hard set to 110V to avoid this. Eventually I replaced the UPSs with better ones and haven’t had the problem since.

But it got me thinking could the same thing happen? I mean pretty much all servers now have auto switching power supplies, and one of this organizations tests involved 208V/220V power sags dropping as low as 60% of regular voltage. Could that convince the power supply it’s time to go to 120V ? I didn’t get to ask..

They constructed a power supply board with some special capacitors I believe they were(they were certainly not batteries but they may of had another technical term that escapes me), which can store enough energy to ride that 2 second window where 90% of power problems occur in. He talked about other components that would assist in the charging of this capacitor, since it was an order of magnitude larger than the regular ones in the system there had to be special safeguards in place to prevent it from exploding or something when it charged up. Again lots of electrical stuff beyond my areas of expertise(and interest really!).

They demonstrated it the lab, and it worked well. He said there really isn’t anything like it on the market, and this is purely a lab thing they don’t plan to make anything to sell. The power supply manufacturers are able to do this, but they are waiting to see if a market develops, if there will be demand in the general computing space to make such technology available.

I’d be willing to bet for the most part people will not use server level batteries. In my opinion it doesn’t make sense unless your operating at really high levels of scale, I believe for the most part people want and need more of a buffer, more of a margin of error to be able to correct things that might fail, having only a few seconds to respond really isn’t enough time. At certain scale it becomes less important but most places aren’t at that scale. I’d guesstimate that scale doesn’t kick in until you have high hundreds or thousands of systems, preferably at diverse facilities. And most of those systems have to be in like configurations running similar/same applications in a highly redundant configuration. Until you get there I think it will still be very popular to stick with redundant power feeds and redundant UPSs. The costs to recover from such a power outage are greater than what you gain in efficiency(in my opinion).

In case it’s not obvious I feel the same way about flywheel UPSs

Airflow Optimization

Another breakout session was about airflow optimization. The one interesting thing I learned here is that you can measure how efficient your airflow is by comparing the temperature of the intake of the AC units vs the output of them. If the difference is small (sub 10 degrees) then there is too much air mixture going on. If you have a 100% efficient cooling system it will be 28-30 degrees difference. He also mentioned that there isn’t much point in completely isolating thermal zones from each other unless your running high densities(at least 8kW per rack). If your doing less the time for ROI is too long for it to be effective.

He mentioned one customer that they worked with, they spent $45k on sensors(350 of them I think), and a bunch of other stuff to optimize the airflow for their 5,000 square foot facility. While they could of saved more by keeping up to 5 of their CRAH(?) units turned off(AC units), the customer in the end wanted to keep them all on they were not comfortable operating with temps in the mid 70s. But despite having the ACs on, with the airflow optimization they were able to save ~5.7% in power which resulted in something like $33k in annual savings. And now they have a good process and equipment to be able to repeat this procedure on their own if they want in other locations.

Other stuff

There was a couple other breakout sessions I went to, one from some sort of Wall Street research firm, which really didn’t seem interesting, he mostly talked about what his investors are interested in(stupid things like the number of users on Twitter and Facebook – if you know me you know I really hate these social sites)

Then I can’t leave this blog without mentioning the most pointless breakout session ever, sorry no offense to the person who put it on, it was about Developing Cloud Services. I really wasn’t expecting much but what I got was nothing. He spent something like 30 minutes talking about how you need infrastructure, power, network, support etc. I talked with another attendee who agreed this guy had no idea what he was talking about he was just rambling on about infrastructure(he works for a data center company). I can understand talking about that stuff but everything he covered was so incredibly obvious it was a pointless waste of time.

Shameless Plug

If your building out a datacenter with traditional rack mount systems and can choose what PDU you use I suggest you check out Servertech stuff, I really like them for their flexibility but they also on their higher end models offer integrated environmental sensors, if you have 2 PDUs per rack as an example you can have up to 4 sensors(two in front, two in back yes you want sensors in back). I really love the insight that massive instrumentation gives. And it’s nice to have this feature built into the PDU so you don’t need extra equipment.

Servertech also has software that integrates with server operating systems which can pro-actively gracefully shut down systems(in any order you want) as the temperature rises in the event of a cooling failure, they call it Smart Load Shedding.

I think they may also be unique in the industry in having a solution that can measure power usage on a per-outlet basis. And they claim something like accuracy within 1% or something. I recall asking another PDU manufacturer a few years ago on the prospects of measuring power on a per-outlet basis and they said it was too expensive, it would add ~$50 per outlet monitored. I don’t know what Servertech charges for these new CDUs (as they call them), but I’m sure they don’t charge $50/outlet more.

There may be other solutions in the industry that are similar, I haven’t found a reason to move away from Servertech yet. My previous PDU vendor had some pretty severe quality issues(~30% failure rate), so of course not all solutions are equal.

Conclusion

The conclusion to this is it pretty much lived up to my expectations. I would not pay for this event to attend it unless I was building/designing data centers. The sales guys from Datacenter Dynamics tried to convince me that it would be of value to me, and on their site they list a wide range of professions that can benefit from it. Maybe it’s true, I learned a few things, but really nothing that will cause me to adjust strategy in the near future.

April 26, 2010

40GbE for $1,000 per port

Filed under: Networking,News — Tags: , — Nate @ 8:32 am

It seems it wasn’t too long ago that 10GbE broke the $1,000/port price barrier. Now it seems we have reached it with 40GbE as well, from my own personal favorite networking company Extreme Networks, announced today the availability of an expansion module for the X650 and X480 stackable switches to include 40GbE support. Top of rack line rate 10GbE just got more feasable.

LAS VEGAS, NV, Apr 26, 2010 (MARKETWIRE via COMTEX News Network) — Extreme Networks, Inc. (NASDAQ: EXTR) today announced highly scalable 40 Gigabit Ethernet (GbE) network solutions at Interop Las Vegas. The VIM3-40G4X adds four 40 GbE connections to the award-winning Summit(R) X650 Top-of-Rack stackable switches for $3,995, or less than $1,000 per port. The new module is fully compatible with the existing Summit X650 and Summit X480 stackable switches, preserving customers’ investments while providing a smooth upgrade to greatly increased scalability of both virtualized and non-virtualized data centers.

[..]

Utilizing Ixia’s IxYukon and IxNetwork test solutions, Extreme Networks demonstrates wire-speed 40Gbps performance and can process 60 million packets per second (120Mpps full duplex) of data center traffic between ToR and EoR switches.

April 19, 2010

Arista ignites networks with groundbreaking 10GbE performance

Filed under: Networking,News — Tags: , — Nate @ 8:53 am

In a word: Wow

Just read an article from our friends at The Register on a new 384-port chassis 10GbE switch that Arista is launching. From a hardware perspective the numbers are just draw dropping.

A base Arista 7500 costs $140,000, and a fully configured machine with all 384 ports and other bells and whistles runs to $460,800, or $1,200 per port. This machine will draw 5,072 watts of juice and take up a little more than quarter of a rack.

Compare this to a Cisco Nexus 7010 setup to get 384 wirespeed ports and deliver the same 5.76 Bpps of L3 throughput, and you need to get 18 of the units at a cost of $13.7m. Such a configuration will draw 160 kilowatts and take up 378 rack units of space – nine full racks. Arista can do the 384 ports in 1/34th the space and 1/30th the price.

I love the innovation that comes from these smaller players, really inspiring.

April 14, 2010

First SPC-1 Numbers with automagic storage tiering

Filed under: News,Storage — Tags: , , , — Nate @ 8:38 am

IBM recently announced that they are adding an “easy tier” of storage to some of their storage systems. This seems to be their form of what I have been calling automagic storage tiering. They are doing it at the sub LUN level in 1GB increments. And they recently posted SPC-1 numbers for this new system, finally someone posted numbers.

Configuration of the system included:

  • 1 IBM DS8700
  • 96 1TB SATA drives
  • 16 146GB SSDs
  • Total ~100TB raw space
  • 256GB Cache

Performance of the system:

  • 32,998 IOPS
  • 34.1 TB Usable space

Cost of the system:

  • $1.58 Million for the system
  • $47.92 per SPC-1 IOP
  • $46,545 per usable TB

Now I’m sure the system is fairly power efficient given that it only has 96 spindles on it, but I don’t think that justifies the price tag. Just take a look at this 3PAR F400 which posted results almost a year ago:

  • 384 disks, 4 controllers, 24GB data cache
  • 93,050 SPC-1 IOPS
  • 26.4 TB Usable space (~56TB raw)
  • $548k for the system (I’m sure prices have come down since)
  • $5.89 per SPC-1 IOP
  • $20,757 per usable TB

The system used 146GB disks, today the 450GB disks seem priced very reasonably, I would opt for those instead and get the extra space for not much of a premium.

Take a 3PAR F400 with 130 450GB 15k RPM disks, that would be about 26TB of usable space with RAID 1+0 (the tested configuration above is 1+0). That would give about 33.8% of the performance of the above 384-disk system, so say 31,487 SPC-1 IOPS, very close to the IBM system and I bet the price of the 3PAR would be close to half of the $548k above (taking into account the controllers in any system are a good chunk of the cost). 3PAR has near linear scalability making extrapolations like this possible and accurate. And you can sleep well at night knowing you can triple your space/performance online without service disruption.

Note of course you can equip a 3PAR system with SSD and use automagic storage tiering as well, they call it Adaptive Optimization, if you really wanted to. The 3PAR system moves data around in 128MB increments by contrast.

It seems the cost of the SSDs and the massive amount of cache IBM dedicated to the system more than offset the benefits of using lower cost nearline SATA disks in the system. If you do that, what’s the point of it then?

So consider me not impressed with the first results of automagic storage tiering. I expected significantly more out of it. Maybe it’s IBM specific, maybe not, time will tell.

April 9, 2010

Found a use for the cloud

Filed under: News,Virtualization — Tags: — Nate @ 1:42 pm

Another interesting article on Datacenter Knowledge and mentioned the U.S. Government’s use of the Terremark cloud, I recall reading about it briefly when it first launched but seeing the numbers again made me do another double take.

”One of the most troubling aspects about the data centers is that in a lot of these cases, we’re finding that server utilization is actually around seven percent,” Federal Chief Information Officer Vivek Kundra said

[..]

Yes, you read that correctly. A government agency was going to spend $600,000 to set up a blog.

[..]

The GSA previously paid $2.35 million in annual costs for USA.gov, including $2 million for hardware refreshes and software re-licensing and $350,000 in personnel costs, compared to the $650,000 annual cost to host the site with Terremark.

For $650k/yr I bet the site runs on only a few servers(dozen or less) and has less than a TB of total disk space.

April 8, 2010

What can you accomplish in two microseconds?

Filed under: Networking — Nate @ 4:30 pm

An interesting post on the Datacenter Knowledge site about the growth in low latency data centers, the two things that were pretting shocking to me at the end were:

“I still find it amazing,” said McPartland. “A blink of an eye is 300 milliseconds. That’s an eternity in this business.”

How much of an eternity: “You can do a heck of a lot in 2 microseconds,” said Kaplan.

Interesting the latency requirements these fast stock traders are looking for, reminded me of a network upgrade the NYSE did deploying some Juniper stuff a while back as reported by The Register:

With the NewYork Stock Exchange down on Wall Street being about ten miles away from the data center in New Jersey, the delay between Wall Street and the systems behind the NYSE is about 105 microseconds. This is not a big deal for some trading companies, but means millions of dollars for others.

[..]

NYSE Technologies, which is the part of the company that actually hooks people into the NYSE and Euronext exchanges, has rolled out a market data system based on the Vantage 8500 switches. The system offers latencies per core switch in the range of 25 microseconds for one million messages per second on messages that are 200 bytes in size.

The Vantage 8500 switch seems pretty scalable, claiming to have non blocking scalability of 10GbE for up to 3,400 servers, announced last year.

Arista Networks somewhat recently launched an initiative aimed at this market segment as well.

Since the Juniper announcement, Force10 announced that the NYSE has chosen their gear for the next generation data centers at the NYSE, the Juniper switching gear so far hasn’t looked all that great compared to the competition, so I’d be curious how the deployment of Force10 stuff relates to the earlier deployment of Juniper stuff:

SAN JOSE, Calif., November 9, 2009 – Force10 Networks, Inc., the global technology leader that data center, service provider and enterprise customers rely on when the network is their business, today announced that the NYSE Euronext has selected its high-performance 10 Gigabit Ethernet (10 GbE) core and access switches to power the management network in their next-generation data centers in the greater New Jersey and London metro areas.

Force10 of course has been one of the early innovators and leaders in 10GbE port density and raw throughput(at least on paper, I’ve never used their stuff personally though have heard good things). On a related note it wasn’t long ago that they filed for an IPO, I wish them the best, as Force10 really is an innovative company and I’ve admired their technology for several years now.

(how do I remember all of these news articles?)

« Newer PostsOlder Posts »

Powered by WordPress